This application procedure applies to Domestic (below 25kVA) and Premium applications (Above 25kVA, excluding SMEs with a load between 100kVA to 200kVA). This includes Additional Load and Meter Separation applications.
1. Application
All customers applying electricity are encouraged to make application online on https://selfservice.kplc.co.ke.
2. Quotation
You will receive a quotation based on your specifications in your enquiry.
The following quotation timelines will apply for various application types;
A quotation is valid for ninety (90) days within which payment can be made via Mobile money (Pay bill number 888899, Account No: application reference No.)
3. Construction & Metering
KPLC will obtain necessary consent where applicable to lay electricity supply lines and thereafter undertake construction and metering within the following timelines;
Customer Checklist
1. Application
All customers applying electricity are encouraged to make application online on https://selfservice.kplc.co.ke.
Submit applicable documents (refer to customer checklist below). You will be provided with an Application Reference Number instantly.
2. Quotation
You will receive a quotation based on your specifications in your enquiry.
The following quotation timelines will apply for various application types;
3. Construction & Metering
KPLC will obtain necessary consent where applicable to lay electricity supply lines and thereafter undertake construction and metering within the following timelines;
Please attach the following documents when submitting your enquiry for supply form:
- Copy of National Identification (I.D) or Passport for Non-Kenyans/ Company Registration Certificates
- Copy of your KRA PIN Certificate
- Route sketch map leading to premises where supply is required.
- Copy of title deed and land search documents for ownership of property (to support way leaves consent).
- Duly filled Supply Contract form (accessible here https://bit.ly/3btxjVq)
- Wiring Certificates (Submit any time after issuance of application reference number but before construction of the electricity network)
- Copy of latest Electricity Bill
Additional Requirements for Premium Applications (Businesses)